We previously advised residents that the work to extend the platforms at Freshford Station was due to start in late January, for completion by the end of March.
As it was clear that nothing has been happening we contacted Network Rail to find out where things have got to.
They apologise for not keeping us informed but say that there has been a delay “due to design delays”.
They have now advised a new schedule, see below.
Activity Name | Start | Finish | Enabling Works | 19/02/2018 | 07/04/2018 | Install access trackway | 19/02/2018 | 23/02/2018 | Site Compound | 26/02/2018 | 02/03/2018 | De-vegetation | 01/03/2018 | 01/03/2018 | Preparation works - embankment re-profile | 02/04/2018 | 05/04/2018 | Remove access ramps | 06/04/2018 | 07/04/2018 | New Platform Extension - Platform 1 | 08/04/2018 | 15/04/2018 | New Platform Extension - Platform 2 | 05/03/2018 | 20/04/2018 | Existing Platform Works - Platform 1 | 02/03/2018 | 13/04/2018 | Existing Platform Works - Platform 2 | 03/03/2018 | 20/04/2018 | Finishing Works | 21/04/2018 | 11/05/2018 |
|