Safety improvements on A36

posted 23 May 2015, 00:42 by Parish Council Communications
Residents will be aware that Skanska, on behalf of Highways England, are currently carrying out a major geotechnical scheme on the A36 at Claverton.  They also need to carry out essential safety improvements along the A36 at 10 separate locations.  These will include a variety of improvements including improved signing, new road markings, high friction surface treatment, patching, red surfacing and vegetation clearance.  They have decided to carry out these safety improvements at the same time as the geotechnical scheme in a bid to minimise disruption in the future.

The safety works will start on Monday, June 1st, and will last approximately four weeks, with both day time and night time working taking place.  The majority of the work will be carried out using temporary traffic signals but at times it will be necessary to close certain parts of the road to ensure safety. During this time, local diversions will be put in place and signage will be on display.  Below you will see a programme of where they will be at times throughout the works. These times and dates are approximate only and are subject to change:

Site 1: North of Claverton/Dundas. Out of Bath on approach to junction with Down Lane
17/06/15 to 19/06/15 - 2 way signals. Night time working. 

Site 2: North of Claverton/Dundas. Northern junction to Claverton
01/06/15 to 02/06/15 - 3 way signals. Night time working.

Site 3: North of Claverton/Dundas. Southern junction to Claverton
02/06/15 to 03/06/15 - 3 way signals. Night time working.

Site 4: North of Claverton/Dundas. Monkton Combe Garage
01/06/15 and 04/06/15 - 3 way signals. Night time working.

Site 5: South of Claverton/Dundas. Pipehouse Lane crossroads
01/06/15 and 03/06/15 - 3 way signals daytime working 
02/06/15 - 3 way signals. Night time working.

Site 6: South of Claverton/Dundas. A366, Wick Farm Junction
03/06/15 to 04/06/15 and 10/06/15 - 3 way signals. Night time working.
15/06/15 - 2 way signals. Night time working.

Site 7: South of Claverton/Dundas.A366, Norton St Philips Junction
11/06/15 - 3 way signals. Night time working.
16/06/15 - 2 way signals. Night time working.

Site 8: South of Claverton/Dundas. North of Woolverton and outside the Red Lion
05/06/15 and 08/06/15 - 2 way signals. Night time working.

Site 9: South of Claverton/Dundas. South of Woolverton
05/06/15 and 09/06/15 - 3 way signals. Night time working.

Site 10: South of Claverton/Dundas. Standerwick outside the Bell Inn
12/06/15 - 3 way signals. Night time working.
22/06/15 to 24/06/15 - 2 way signals. Night time working.

If you have any queries or comments please contact the Highways England Information Line on 0300 123 5000.